Code: 03ROAD3021  
Category/Planning Area: Local / Area 3  
Location: St Georges Basin  
Description: The Wool Road Bypass  
Strategy: To provide improved, efficient and safe public road networks for increasing traffic volumes associated with development demand.
Contribution Rate:
Table control
Contribution map shaded areas indicate the Contribution Area(s). Red indicates Contribution Infrastructure.
View Larger Map (PDF)
Project Estimate: $5,123,898.00 in Dec 2009
Indexed Estimate:
Apportionment: Recoupment of cost apportioned to future development is 16.72%.
Nexus: The project ensures that new development pays an equitable apportionment of costs associated with providing a suitable road network which directly services demand created by development. The demand for this project includes 9.6% assumed through traffic. This equates to $491,246 in Dec 2009 which is apportioned to Council.
Supporting Information:
Supporting Information can be found here.
Proposed Works: Not Applicable. The project has been completed.
Land Acquisition Estimate: $0.00
Timing: Not Applicable. The project has been completed.
     
  Plan Effective: 23 Mar 2011 - As Amended (September 2014)