Code: 03ROAD0059  
Category/Planning Area: Local / Area 3  
Location: Huskisson  
Description: Field Street Turning Circle  
Strategy: To provide improved, efficient and safe public road networks associated with future development demand.
Contribution Rate:
Table control
Contribution map shaded areas indicate the Contribution Area(s). Red indicates Contribution Infrastructure.
View Larger Map (PDF)
Project Estimate: $214,780.00 in Jul 2012
Indexed Estimate:
Apportionment: The apportionment to future development is 44.6%.
Nexus: The project ensures that new development pays an equitable apportionment of costs associated with providing a suitable road network which directly services demand created by development.
Supporting Information: Supporting Information can be found here.
Proposed Works: See Supporting Information
Land Acquisition Estimate: $0.00 in Jul 2012
Timing: Development Dependent
     