Code: 03DRAI2001  
Category/Planning Area: Local / Area 3  
Location: St Georges Basin  
Description: St Georges Basin Village Centre Drainage  
Strategy: To facilitate provision of an integrated drainage network connected to Council’s existing system to minimise overflow and environmental impacts
Contribution Rate:
Table control
Contribution map shaded areas indicate the Contribution Area(s). Red indicates Contribution Infrastructure.
View Larger Map (PDF)
Project Estimate: $1,134,740.00 in Jun 2009
Indexed Estimate:
Apportionment: The apportionment to future development is 73.08%.
Nexus: The project is required to sustain development within the identified catchment / contribution area. An upgrade of the existing network generally along Collett Place forms part of this project. The upgrade work will provide for existing stormwater flows as well as the expected additional flows generated from development areas, so 50% of the upgrading costs will be borne by Council. This equates to $305,430 in June 2009.
Supporting Information: Supporting Information can be found here.
Proposed Works: See supporting information.
Land Acquisition Estimate: $0.00
Timing: 2009/13
     
  Plan Effective: 23 Mar 2011 - As Amended (September 2014)