Code: |
03CFAC3001
|
|
Category/Planning Area: |
Local / Area 3
|
|
Location: |
Vincentia
|
|
Description: |
Bay & Basin Community Centre and Branch Library
|
|
Strategy: |
To provide the community with increased variety of activity and access to Information Technology that meets with user needs of growing social development demand.
|
|
Contribution Rate: |
Table control
|
|
View Larger Map (PDF)
|
Contribution map shaded areas indicate the Contribution Area(s). Red indicates Contribution Infrastructure.
|
Project Estimate: |
$7,379,300.00 in May 2004
|
Indexed Estimate:
|
|
Apportionment: |
The apportionment to future development is 22.66%.
|
Nexus: |
The population accommodated in both existing and future development in Planning Area 3 up to 2026 will generate all of the need for this project. A more specific apportionment approach taking account of existing deficiencies has been applied to the calculation of the library contribution rate. The community centre cost however has been spread evenly over existing and future populations. Refer to supporting information for more details.
|
Supporting Information: |
Supporting Information can be found here.
|
Proposed Works: |
Concept plan is not available.
|
Land Acquisition Estimate: |
$62,900.00 in Mar 2010
|
Timing: |
2015/19
|
|
|
|
|
Plan Effective:
23 Mar 2011 - As Amended (September 2014)
|
|