Code: 03AREC3003  
Category/Planning Area: Local / Area 3  
Location: Vincentia  
Description: Bay and Basin Leisure Centre (The Wool Road, Vincentia)  
Strategy: To provide leisure centre facilities to meet anticipated demand from development.
Contribution Rate:
Table control
Contribution map shaded areas indicate the Contribution Area(s). Red indicates Contribution Infrastructure.
View Larger Map (PDF)
Project Estimate: $749,931.00 in Jan 2010
Indexed Estimate:
Apportionment: Recoupment of cost apportioned to future development is 100%.
Nexus: The population accommodated in Planning Area 3 in both existing and future development up to 2026 will generate the demand for this project. The contribution rate calculation therefore reflects this planning philosophy. When this project was opened in May 1999 the apportionment to development was 19.53%. The recoupment of the remaining cost owed by development is apportioned to 100%.
Supporting Information:
Supporting Information can be found here.
Proposed Works: Not applicable. The project has been completed.
Land Acquisition Estimate: $0.00
Timing: Not Applicable. The project has been completed.
     
  Plan Effective: 23 Mar 2011 - As Amended (September 2014)