Code: 01ROAD2133  
Category/Planning Area: Local / Area 1  
Location: Berry  
Description: Beach and Tannery Road upgrade (road and bridge) related to quarry works  
Strategy: To maintain safe public road networks associated with quarry works.
Contribution Rate:
Table control
Contribution map shaded areas indicate the Contribution Area(s). Red indicates Contribution Infrastructure.
View Larger Map (PDF)
Project Estimate: $284,167.00 in Sep 2008
Indexed Estimate:
Apportionment: The apportionment to future development is 100%.
Nexus: The project is to ensure that quarry transport pays an equitable apportionment of costs associated with maintaining a suitable road network. The maintenance rate is as per the rate established in Amendment 71 of Council's 1993 Cotnributions Plan.
Supporting Information:
Supporting Information can be found here.
Proposed Works: Concept plan is not available.
Land Acquisition Estimate: $0.00
Timing: Ongoing
     
  Plan Effective: 23 Mar 2011 - As Amended (September 2014)