Code: 01ROAD2071  
Category/Planning Area: Local / Area 1  
Location: Barrengary  
Description: Carter’s Road gravel upgrade (For 800ms from Moss Vale Road)  
Strategy: To provide improved, efficient and safe public road networks for increasing traffic volumes associated with development demand.
Contribution Rate:
Table control
Contribution map shaded areas indicate the Contribution Area(s). Red indicates Contribution Infrastructure.
View Larger Map (PDF)
Project Estimate: $111,460.00 in Nov 2005
Indexed Estimate:
Apportionment: The apportionment to future development is 18.75%.
Nexus: The project is critical for ensuring that new development pays an equitable apportionment of costs associated with providing a suitable road network which directly services demand created by development.
Supporting Information:
Supporting Information can be found here.
Proposed Works: Concept plan is not available.
Land Acquisition Estimate: $0.00
Timing: 2014/18
     
  Plan Effective: 23 Mar 2011 - As Amended (September 2014)